Case Study: Long Travel Drive System Upgrade

Design and Supply of New Control System

  • Project:
    Stacker Reclaimer Upgrade
  • Cost:
    £18,000
  • Timescale:
    1 day to commission

Oracle Supplied 8 new 6 pole AC induction motors and a backplate housing a Parker 650V AC drive unit to control the long travel of the stacker Reclaimer.

The installation was completed by the clients own engineering team to keep costs down. Oracle Then commissioned and tested the whole system.

This machine scoops up coke using a rotating bucket as it travels down the linear tracks.

It also stacks up the coke by offloading coal from a conveyor to stockpile the material.

This is the 5th upgrade of its type carried out in recent years.

Before and After

 

 

 

Oracle Drive Systems

Online Store

Why not shop online for your key part. We stock a huge range of new and reconditioned parts ready for immediate despatch.

Case Studies

Read example case studies of the work we do and see how we have helped other businesses.

Oracle News

11/10/2017 - Win upto 8 hours Engineering time

Twitter